Schedule
Lakeview Commons 6-Lot · phases, dependencies, and milestones
Edit per-lot phasesOn schedule
Overall progress
74%
weighted across 6 lots
At Building Final
2
Lots 4 & 6 — by Jul 2
Next milestone
Jul 1
Building Final (Lots 4 & 6)
Projected finish
Sep 18
last final draw (Lots 2 & 5)
Drag a bar to reschedule (linked tasks are pushed forward), drag its right edge to resize, drag the ○ handle onto another row to link a dependency, click an arrow to remove one. Double-click a name to rename, click a task's status icon to pick a status, or focus a bar and use ←/→ (Shift to resize, Enter to cycle status). Set a task's duration to 0 to make it a ◆ milestone.
Complete
10 / 27
In progress
7
Delayed
0
% complete
37%
Lakeview Commons 6-Lot
Apr 2026
May 2026
Jun 2026
Jul 2026
Aug 2026
Sep 2026
Task
▸Sitework & Foundation
✓Earthwork, Drainage & Utilities
12d
✓Foundation & SlabPred: #1
6d
▸Structure & Exterior
✓Framing & StairsPred: #2
Framing & Stairs · 20d
✓Roof Dry-In, Windows & DoorsPred: #3
8d
✓Siding & Exterior PaintPred: #4
12d
▸MEP Rough-In
✓MEP Rough-In (Plumb / Elec / HVAC)Pred: #3
14d
▸Drywall
✓InsulationPred: #6
✓Drywall & TexturePred: #7
13d
▸Interior Finishes
✓Prime CoatPred: #8
6d
✓Stair & Balcony GuardrailsPred: #8
8d
◐Interior DoorsPred: #8
6d
◐TilePred: #8
12d
◐Trim & Finish CarpentryPred: #8
10d
◐CabinetsPred: #8
Cabinets · 22d
◐Wood FlooringPred: #8
12d
○CountertopsPred: #14
8d
○AppliancesPred: #16
○Final Paint & Touch-UpPred: #14, #15
8d
▸MEP Trim & Finals
◐Electrical Trim-OutPred: #9
10d
○HVAC Set & Start-UpPred: #19
10d
○Plumbing Trim-OutPred: #16, #17, #12
6d
○Trade Final InspectionsPred: #21, #19, #18
▸Closeout
◐Building Final — Lots 4 & 6Pred: #10
○CO & Final Draw — Lots 4 & 6Pred: #23
8d
○Flatwork, Fence & LandscapingPred: #5
14d
○Building Final — Remaining LotsPred: #22, #25
14d
○CO & Final Draws — Remaining LotsPred: #26
CO & Final Draws — Remaining Lots · 16d
PendingIn progressCompleteDelayed