Builder Portal
12Consolidated tasks for Summit Ridge Builders — action items, open RFIs, open punch, and city inspections needing attention in one feed.
Open tasks
12
High priority
6
Open RFIs
2
Open punch
3
Action
Portfolio · Collect outstanding owner balances — $322,100 owed project-wide; Sofia ($109.6K) and Avery ($106.0K) are the largest
Action
Lot 5 · Draw #4 package ($28,400) awaiting borrower signature — follow up with Sofia Rivera
Action
Lot 2 · Match duplicate $1,842.50 cabinet-hardware card payment (two log entries 04/18/26, one bank deposit)
RFI
Lot 5 · RFI-041 — Beam depth at kitchen opening vs plan (to Summit Ridge Builders)
Punch
Lot 4 · Kitchen: Touch up paint at range hood cutout
Punch
Lot 2 · Stairs: Handrail bracket loose at landing
Action
Lots 4 & 6 · Building Final scheduled Jul 1–2 — confirm driveway flatwork completes this week
Action
Portfolio · Quarterly lender site visit — compile progress photo set for First Gulf Bank
RFI
Lot 4 · RFI-042 — Confirm attic access location (to Summit Ridge Builders)
Punch
Lot 6 · Living: Adjust sliding-door roller — drags at midpoint
Inspection
Lot 4 · Final building — City of Houston (2026-07-01)
Inspection
Lot 6 · Final building — City of Houston (2026-07-02)