First Gulf Bank construction-loan advances that fund the build of your lot. Tap any draw to see what it covered. Separate from your payments to EPEX.

$192,800 of $290,000 advanced
Lot 5
66.48%
DrawAmountCumulative
Draw #1$36,400$36,400 cum
What this draw covered
WorkAmount%
Earthwork$9,00025%
Site utilities$7,40020%
Foundation$20,00055%
Total$36,400100%
Draw #2$71,000$107,400 cum
What this draw covered
WorkAmount%
Framing$55,00077%
Roof & windows$12,00017%
Site drainage$4,0006%
Total$71,000100%
Draw #3$57,000$164,400 cum
What this draw covered
WorkAmount%
MEP rough-in$27,50048%
Insulation & drywall$21,00037%
Exterior progress$8,50015%
Total$57,000100%
Draw #4$28,400$192,800 cum
Draw #4 detail
Date2026-06-18
Amount$28,400
Cumulative$192,800

This draw is funded against the lot’s overall schedule of values. See the full breakdown and percent complete below.

Full schedule of values · contract to date
WorkContractDrawn%
Earthwork$9,000$9,000100%
Site drainage$7,500$7,500100%
Site utilities$7,400$7,400100%
Foundation$23,000$23,000100%
Framing$60,000$60,000100%
Roof & windows$15,000$15,000100%
Exterior siding & paint$13,500$6,00044%
Plumbing$17,500$10,00057%
Electrical$19,000$11,50061%
HVAC$11,600$6,00052%
Insulation & drywall$21,000$21,000100%
Interior doors & trim$9,0000%
Cabinets & countertops$16,000$5,00031%
Tile & flooring$14,500$4,00028%
Interior paint$7,5000%
Appliances$5,0000%
Site paving & landscaping$8,5000%
Builder's fee$17,500$7,40042%
Contingency$7,5000%
Total$290,000$192,80066%

From the signed First Gulf Bank advance-request package. Drawn total ties to $192,800 advanced on your lot.