Your unit · Lot 5 · Unit C
Lakeview Commons 6-Lot Development
Active8800 & 8802 Lakeview Commons Dr, Houston TX · GC: Summit Ridge Builders · Lender: First Gulf Bank
Project cost (your unit)
$290,000
contract value
Funded to date
$164,400
57% of cost
Open balance
$125,600
due at finish-out
Funding progress
57% funded$164,400 paid of $290,000 · $125,600 remaining
Construction progress
Sitework & foundation
Structure & exterior
MEP rough-in
Insulation & drywall
Cabinets
Upcoming milestones
Cabinets
In progress
Tile
Upcoming
Paint
Upcoming
Flooring
Upcoming
Doors & finish carpentry
In progress
Recent activity
RFI-041 opened
Beam depth at kitchen opening vs plan · Lot 5 · 2026-06-11
Check recorded a deposit
$28,000.00 · Lot 5 · 2026-06-10
Alex Morgan added a daily log
Lot 5 cabinet delivery staged in garage; countertop template Monday. Lots 1 & 3 drywall … · 2026-05-22
Change order CO-101 was approved
Upgrade primary bath to frameless glass shower · Lot 5 · 2026-05-18
Square recorded a deposit
$38,000.00 · Lot 5 · 2026-04-15