Lakeview Commons 6-Lot DevelopmentSwitch role →

Draws

First Gulf Bank construction-loan advances that fund the build of your lot. Tap any draw to see what it covered. Separate from your payments to EPEX.

$235,800 of $280,000 advanced
Lot 4
84.21%
DrawAmountCumulative
Draw #1$44,000$44,000 cum
What this draw covered
WorkAmount%
Earthwork$8,60020%
Foundation$22,40051%
Site drainage$7,00016%
Mobilization / site security$6,00014%
Total$44,000100%
Draw #2$68,800$112,800 cum
What this draw covered
WorkAmount%
Framing$52,00076%
Roof & windows$16,80024%
Total$68,800100%
Draw #3$52,000$164,800 cum
What this draw covered
WorkAmount%
MEP rough-in$32,00062%
Insulation & drywall$20,00038%
Total$52,000100%
Draw #4$41,000$205,800 cum
Draw #4 detail
Date2026-05-01
Amount$41,000
Cumulative$205,800

This draw is funded against the lot’s overall schedule of values.

Draw #5$30,000$235,800 cum
Draw #5 detail
Date2026-05-30
Amount$30,000
Cumulative$235,800

This draw is funded against the lot’s overall schedule of values.