Lakeview Commons 6-Lot DevelopmentSwitch role →

Draws

First Gulf Bank construction-loan advances that fund the build of your lot. Tap any draw to see what it covered. Separate from your payments to EPEX.

$231,500 of $300,000 advanced
Lot 2
77.17%
DrawAmountCumulative
Draw #1$42,000$42,000 cum
What this draw covered
WorkAmount%
Earthwork$9,50023%
Foundation$24,50058%
Site drainage$8,00019%
Total$42,000100%
Draw #2$84,500$126,500 cum
What this draw covered
WorkAmount%
Framing$62,00073%
Roof & windows$15,50018%
Site utilities$7,0008%
Total$84,500100%
Draw #3$58,000$184,500 cum
What this draw covered
WorkAmount%
MEP rough-in$36,00062%
Insulation & drywall$22,00038%
Total$58,000100%
Draw #4$47,000$231,500 cum
Draw #4 detail
Date2026-06-08
Amount$47,000
Cumulative$231,500

This draw is funded against the lot’s overall schedule of values. See the full breakdown and percent complete below.

Full schedule of values · contract to date
WorkContractDrawn%
Earthwork$9,500$9,500100%
Site drainage$8,000$8,000100%
Site utilities$7,000$7,000100%
Foundation$24,500$24,500100%
Framing$62,000$62,000100%
Roof & windows$15,500$15,500100%
Exterior siding & paint$14,000$9,00064%
Plumbing$18,000$12,00067%
Electrical$19,500$13,50069%
HVAC$12,000$8,00067%
Insulation & drywall$22,000$22,000100%
Interior doors & trim$9,500$4,00042%
Cabinets & countertops$16,500$8,00048%
Tile & flooring$15,000$9,00060%
Interior paint$8,000$4,00050%
Appliances$5,5000%
Site paving & landscaping$9,0000%
Builder's fee$18,000$9,50053%
Contingency$6,500$6,00092%
Total$300,000$231,50077%

From the signed First Gulf Bank advance-request package. Drawn total ties to $231,500 advanced on your lot.